Put Your AD here!

Feds’ Plan to Decarbonize Canada’s Electricity Grid by 2035 ‘Not Feasible’: Think Tank

Feds’ Plan to Decarbonize Canada’s Electricity Grid by 2035 ‘Not Feasible’: Think Tank


This article was originally published on Epoch Times - World. You can read the original article HERE

The federal government’s plan to make Canada’s electricity generation carbon-free by 2035 is “impractical and highly unlikely” to succeed, the Fraser Institute says, noting that physical, infrastructure, financial, and regulatory realities make the plan “not feasible.”

A new study by the think tank says Ottawa faces a “significant challenge” to its goal of 100 percent decarbonizing the electricity grid in another 10 years alongside its broader aim of achieving net-zero greenhouse gas emissions by 2050.

This transition requires eliminating the remaining use of fossil fuel sources as well as expanding capacity to meet growing demands from electric vehicle adoption, population growth, and industrial electrification, the report from the study indicated.

“Canada’s federal government has set an ambitious, and, frankly, unrealistic target of achieving complete carbon-free electricity in ten years,” said study co-author Jock Finlayson, a senior fellow at the Fraser Institute, in a news release on Oct. 29.

Using data from Statistics Canada, the authors found that in 2023, nearly 81 percent of Canada’s electricity came from carbon-free sources, which included hydro (58.4 percent), nuclear (13.7 percent), wind (6.4 percent), biomass (1.5 percent) and solar (0.8 percent).

Fossil fuels, such as coal, gas and petroleum, accounted for the remaining 19.1 percent. To replace the electricity generated by fossil fuels, Canada will need about 117,700 gigawatt hours (GWh) of electricity to be supplied by carbon-free sources each year, “assuming no growth in overall electricity supply,” said the report by Finlayson along with co-author Elmira Aliakbari, director of the Centre for Natural Resources Studies at the Fraser Institute.

Lands Required

Using hydro power as the sole alternative to replace that remaining fossil fuel-based generation would require building approximately 23 large hydroelectric dams, similar in generation capacity to B.C’s Site C facility, or 24 projects comparable to Newfoundland and Labrador’s Muskrat Falls, the report said.

“These numbers are determined by dividing 117,696 by 5,100 GWh and 4,900 GWh, which are the expected annual outputs of the Site C project and Muskrat Falls project, respectively,” stated the report.

If solely wind energy were to be used to replace that fossil fuel-based electricity, the authors calculated that Canada would need to build around 11,000 large wind turbines across the country by 2035. The calculation assumes a capacity of 3.5 megawatts per turbine and a capacity factor of 35 percent.

“[The turbines] would require approximately 7,302 square kilometres of land—larger than Prince Edward Island and nearly nine times the size of Calgary,” the co-authors wrote. “Hydropower projects would require even more land, about 26,345 square kilometers, nearly half the size of Nova Scotia.”

If nuclear power were solely to be used to replace that fossil fuel electricity, the report said approximately 2.3 large-scale nuclear plants, equivalent to Ontario’s Bruce Power generating station, would have to be built in the next decade. “Assuming Bruce Power operates 8,760 hours a year (that is, 365 × 24) at 90% capacity, this would mean the facility generates 50,458 GWh of electricity annually.” it added.

‘Cost Overruns’

The authors said the current process of planning and constructing major electricity generation facilities in Canada is complex and often marked by “delays, regulatory challenges, and significant cost overruns.”

An example they cited is the Site C project in B.C., which took about 43 years from the initial engineering studies in 1971 to environmental certification in 2014. Site C, expected to be completed in 2025, faced cost challenges during its construction phase.

“Construction finally began in July 2015, but significant cost overruns soon emerged. By 2017, the project’s cost had risen from $8.3 billion to $10.7 billion, and by 2021, it had increased to $16 billion,” the report said.

Co-author Aliakbari says the scale of infrastructure needed to be planned, approved, financed, and built to decarbonize Canada’s electricity grid in just 10 years is “not at all realistic” given that the requirements mentioned in the report would only meet the country’s existing electricity needs.

“This doesn’t even account for the additional infrastructure needed to meet future electricity demand,” Aliakbari said.

The Epoch Times reached out to Environment and Climate Change Canada for comments but did not hear back by publication time.

This article was originally published by Epoch Times - World. We only curate news from sources that align with the core values of our intended conservative audience. If you like the news you read here we encourage you to utilize the original sources for even more great news and opinions you can trust!

Read Original Article HERE



YubNub Promo
Header Banner

Comments

  Contact Us
  • Postal Service
    YubNub Digital Media
    361 Patricia Drive
    New Smyrna Beach, FL 32168
  • E-mail
    admin@yubnub.digital
  Follow Us
  About

YubNub! It Means FREEDOM! The Freedom To Experience Your Daily News Intake Without All The Liberal Dribble And Leftist Lunacy!.


Our mission is to provide a healthy and uncensored news environment for conservative audiences that appreciate real, unfiltered news reporting. Our admin team has handpicked only the most reputable and reliable conservative sources that align with our core values.